Team Member Project Milestones and Testing Strategy

Septembr

Hyrum -

  1. Finish making smart shoes by Friday, 9/15
  2. Have parts for prototype smart wardrobe (work with Rolando) by Friday, 9/15
  3. Complete LED leaf/sensor (work with Rolando) by end of Sept

Jessika -

  1. Make custom control function for light leaf/sensor that works with Arduino by Friday, 9/15
  2. Make emergency and health leaf/sensors by end of Sept
  3. Complete initial smart clothing prototype (work with Saoud) by end of Sept

Rolando -

  1. Have parts for prototype smart wardrobe (work with Hyrum) by Friday, 9/15
  2. Complete LED leaf/sensor (work with Hyrum) by end of Sept
  3. Complete Arc Reactor by end of Sept

Saoud -

  1. Complete Arduino programming communication with app by Friday, 9/15
  2. Make schematic of wiring everything to Arduino by Friday, 9/15
  3. Research batteries we can use for smart clothes, how to check battery %, how to charge them by end of Sept
  4. Complete initial smart clothing prototype (work with Jess) by end of Sept

Testing strategy for app functionality (Jess, Saoud)-- To test the app's functionality we will connect the app to the Arduino via BLE and test all our app features to make sure that everything works as expected.
Initial prototype of smart clothes (Rolando)-- The first working prototype may not have all the features yet, it will probably only have the LED leaf; test it we will use our app to change the LED color (while ensuring nothing explodes or burns).
Smart shoes prototype testing (Hyrum)-- To test the smart shoes we will simply ensure that it automatically self-ties when it detects someone putting on the shoes.

October

Hyrum -

  1. Complete prototype smart wardrobe (work with Rolando) by Friday, 10/14
  2. Complete sensor functionality with prototype smart wardrobe (work with Rolando) by end of Oct

Jessika -

  1. Complete emergency and health leaf/sensor app customization (work with Saoud) by Friday, 10/14
  2. Design and begin implementing modular sensor connection on smart clothes (work with Saoud) by end of Oct

Rolando -

  1. Complete prototype smart wardrobe (work with Hyrum) by Friday, 10/14
  2. Complete sensor functionality with prototype smart wardrobe (work with Hyrum) by end of Oct

Saoud -

  1. Complete testing for the emergency and health leaf/sensors (work with Jess) by Friday, 10/14
  2. Design and begin implementing modular sensor connection on smart clothes (work with Saoud) by end of Oct

Testing strategy for smart wardrobe (Hyrum, Rolando)--- To test it we are going to make sure it's solid enough and safe to use.
Testing strategy for initial smart clothes prototype (Jessika, Saoud)-- We will test our refined design similarly to our first prototype + adding all other leaves and making sure the app can control all leaves.

November

Everyone -

  • Finish the smart wardrobe with all the features by the end of Nov
  • Finish the final design for the smart clothing by the end of Nov

Testing strategy for smart wardrobe (everyone)-- We will test our wardrobe by making sure it's safe to use and it can charge and store leaves easily.
Testing strategy for smart clothes (everyone)-- We will test our final design to make sure all part locations and software are finalized, and that all leaves are easily swappable.

December

Everyone -

  • Finish testing and prep for final demo