windkostya asked this question in Q&A
Discussion options

You must be logged in to vote

Plotting consists of 4 phases but each phase can have sub-phases. The first number stands for the phase and the second for the sub-phase.
In your case 3:6 equals to phase 3, sub-phase 6 (almost done).