reasons to do soon
- WA state sustainable production incentives expire in 2020
- 30% federal tax credit starts shrinking in 2019
- WA state sales tax exemption
todo
- get quotes from installers
- Sunergy: 9.90 kW for $30,424
- NW Wind & Solar: 9.86 kW for $33,341
- Puget Sound Solar: 8.1 kW for $32,762
- choose installer
- schedule installation
- panel installation
- permitting, ~7 days
- Fill out SCL interconnection agreement
- interconnection approval, ~7 days
- install panels on roof (starting May 19th).
- electrical inspection (May 24)
- install new production and digital net meters, ~7-10 days (expected May 31, actual June 8)
- get "made in WA" confirmation, 30 days (June 6)
- receive 30% Federal tax credit (Federal Tax Incentives #70)
options
- put panels on East/West facing garage roof
- roof is nearly new
- put panels on South facing house roof
- depends on two South roofs are aged #18 (replace roofing)
See also
- Roofing
- building code requirements at mybuildingpermit.com
- related to electrical system upgrades & capacity planning #15 (electrical system)