Notifications
You must be signed in to change notification settings - Fork 0
/
_index-slidify.Rmd
86 lines (72 loc) · 3.51 KB
/
_index-slidify.Rmd
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
---
title : EOQ & EPQ Calculators
subtitle : Web-based Economic Order Quantity & Economic Production Quantity Calculation
author : Steve Myles
job : January 2016
framework : io2012 # {io2012, html5slides, shower, dzslides, ...}
highlighter : highlight.js # {highlight.js, prettify, highlight}
hitheme : zenburn #
widgets : [mathjax] # {mathjax, quiz, bootstrap}
mode : standalone # {standalone, draft}
knit : slidify::knit2slides
---
<style>
strong { font-weight: bold; }
em { font-style: italic; }
</style>
## Background
* **Economic Order Quantity (EOQ)**
* a classic model in production scheduling
* results in the optimal order quantity that should be purchased with each order
to *minimize the total cost*
* **total cost** = the cost of holding excess inventory plus the cost of
placing orders
* **Economic Production Quantity (EPQ)**
* an extension of the EOQ model that assumes that the company will produce its
own inventory
* There is [a new online EOQ & EPQ Calculator](https://scumdogsteev.shinyapps.io/eoq-epq) ([GitHub repo](https://github.com/scumdogsteev/eoq-epq))
* based on user inputs, this tool calculates the EOQ and EPQ as well as related
costs
* Extensions to both models exist that allow for inclusion of shortage
(stockout) and back-ordering costs, as well as minimum order quantities (MOQ)
* these extensions are outside the scope of this tool
---
## Formulas
* **EOQ** and **EPQ** are both functions of annualized demand $R$, cost per
order $C$ (not dependent on the quantity ordered), unit cost $P$ (price for EOQ,
production cost for EPQ), and holding cost $H$ (defined as a percentage $F$ of
unit cost, so $H = PF$)
* Additionally, **EPQ** is a function of production rate (units produced per day)
$p$ and demand rate (daily demand) $r$
* Derivations: [EOQ](https://en.wikipedia.org/wiki/Economic_order_quantity#The_total_cost_function_and_derivation_of_EOQ_formula) | [EPQ](https://en.wikipedia.org/wiki/Economic_production_quantity#Total_cost_function_and_derivation_of_EPQ_formula)
* EOQ: $$Q^* = \sqrt{\frac{2CR}{H}} = \sqrt{\frac{2CR}{PF}}$$
* EPQ: $$Q^* = \sqrt{\frac{2CRp}{H(p - r)}}$$
---
## Economic Order Quantity Example
```{r eoq}
eoq <- function(demand, order_cost, holding_cost_percent, unit_cost) {
sqrt(2 * order_cost * demand /
## avoid division by 0 by setting 0% holding cost to 0.001
(ifelse(holding_cost_percent == 0, 0.001, holding_cost_percent) * unit_cost)) }
demand <- 1000; order_cost <- 10; holding_cost_percent <- 0.1; unit_cost <- 5
eoqty <- eoq(demand, order_cost, holding_cost_percent, unit_cost)
eoqty
```
* For the above scenario, the EOQ is `r eoqty`
* If this reflected the need to order a partial unit, one would need to round up
to meet demand
---
## Economic Production Quantity Example
```{r epq}
demand_rate <- function(demand) {demand / 250}
epq <- function(demand, order_cost, holding_cost_percent, unit_cost, production_rate) {
sqrt(2 * order_cost * demand * production_rate /
((ifelse(holding_cost_percent == 0, 0.001, holding_cost_percent)
* unit_cost) * (production_rate - demand_rate(demand)))) }
production_rate <- 5 ## the other parameters are the same as those in the EOQ example
epqty <- epq(demand, order_cost, holding_cost_percent, unit_cost, production_rate)
epqty
```
* For the above scenario, the EPQ is `r round(epqty, 1)`
* Each production run should be `r ceiling(epqty)` in this case (assuming
partial units cannot be produced)