Codewind sprint process is a two week agile sprint starting on Thursday and completing on Wednesday two weeks later. Codewind cuts a formal release every 4 weeks delivering monthly releases.
| Sprint | Dates |
|---|---|
| M23 | Oct 24 - Nov 6 |
| M24 | Nov 7 - Nov 20 |
| M25 | Nov 21 - Dec 4 |
| M26 | Dec 5 - Dec 18 |
| Sprint | Dates |
|---|---|
| 20.1 | Dec 26 - Jan 8 |
| 20.2 | Jan 9 - Jan 22 |
| 20.3 | Jan 23 - Feb 5 |
| 20.4 | Feb 6 - Feb 19 |
| 20.5 | Feb 20 - Mar 4 |
| 20.6 | Mar 5 - Mar 18 |
| 20.7 | Mar 19 - Apr 1 |
| 20.8 | Apr 2 - Apr 15 |
| 20.9 | Apr 16 - Apr 29 |
| 20.10 | Apr 30 - May 13 |
| 20.11 | May 14 - May 27 |
| 20.12 | May 28 - June 10 |
| 20.13 | Jun 11 - June 24 |
| 20.14 | June 25 - July 8 |
| 20.15 | Jul 9 - July 22 |
| 20.16 | Jul 23 - Aug 5 |
| 20.17 | Aug 6 - Aug 19 |
| 20.18 | Aug 20 - Sep 2 |
| 20.19 | Sep 3 - Sept 16 |
| 20.20 | Sep 17 - Sept 30 |
| 20.21 | Oct 1 - Oct 14 |
| 20.22 | Oct 15 - Oct 28 |
| 20.23 | Oct 29 - Nov 11 |
| 20.24 | Nov 12 - Nov 25 |
| 20.25 | Nov 26 - Dec 9 |