Skip to content

Commit

Permalink
final changes
Browse files Browse the repository at this point in the history
  • Loading branch information
masapr committed Aug 22, 2023
1 parent 5413c4b commit a43de34
Showing 1 changed file with 12 additions and 12 deletions.
24 changes: 12 additions & 12 deletions applications/sarp-2-swdesign.md
Original file line number Diff line number Diff line change
Expand Up @@ -92,9 +92,9 @@ The overall conclusion was, that it is best to run the analysis only on the newl

### Overview

- **Total Estimated Duration:** <mark>1 month
- **Full-Time Equivalent (FTE):** <mark>1 FTE
- **Total Costs:** <mark>XXX USD
- **Total Estimated Duration:** 4 months
- **Full-Time Equivalent (FTE):** 0.8 FTE
- **Total Costs:** 100'000 USD

In our previous work, we found the following problems:

Expand Down Expand Up @@ -128,9 +128,9 @@ We plan to do a detailed analysis on interesting vulnerabilities in the [future]


### Milestone 1 - Basic Setup & Mocking of Substrate Libraries
- **Estimated duration:** <mark>1 month
- **FTE:** <mark>1
- **Costs:** <mark>XXX USD
- **Estimated duration:** 2 months
- **FTE:** 0.7
- **Costs:** 47'000 USD

With the first milestone we want to do the basic setup of the project, integrate a first set of substrate mocks and deliver a first runnable tool.

Expand All @@ -144,9 +144,9 @@ With the first milestone we want to do the basic setup of the project, integrate
| 2. | Engagement | Engage with teams at Web3 Foundation and Parity for prioritization. |

### Milestone 2 - Annotations Generator
- **Estimated duration:** <mark>1 month
- **FTE:** <mark>1
- **Costs:** <mark>XXX USD
- **Estimated duration:** 1.5 month
- **FTE:** 0.8
- **Costs:** 37'000 USD

In the second milestone we implement the annotations generator (needed for step 2.ii. of the workflow process).

Expand All @@ -160,9 +160,9 @@ In the second milestone we implement the annotations generator (needed for step
| 2. | Engagement | Engage with teams at Web3 Foundation and Parity for prioritization. |

### Milestone 3 - Complete Tool with Documentation
- **Estimated duration:** <mark>1 month
- **FTE:** <mark>1
- **Costs:** <mark>XXX USD
- **Estimated duration:** 0.5 month
- **FTE:** 1
- **Costs:** 16'000 USD

In the final milestone we finetune the tool, making sure it runs on productive pallet code and write the final documentation.

Expand Down